The schedule is the first tab on the job page. Each task is a bar. The planner places the bars itself, by the order of the stages, the dependencies and the hours of work.

How to read the schedule

  • A day is a working day. The planner uses the Slovak working calendar and skips weekends and public holidays. Every "d" and every "days" means working days.
  • Hours become days by the company's working day (set in the company profile).
  • It is a forecast. Unfinished work never lies in the past; it moves forward from today. A finished task keeps its dates, and if it was finished early, it ends on the day it was finished.
  • The Critical path is the chain of tasks that sets the end date. If any of them moves by a day, the end of the whole job moves.
  • Slack on a task says how long it can be late without moving the end.
  • Deadline is the mark of the job's or the task's deadline. A bar that goes past it is marked.
  • Lead time — a row with a length and no person (a delivery time, a screed curing). It is not work: it has no hours, nobody works on it, and it is never "unassigned".
  • You can change the scale to Days, Weeks, Months or Quarters.

Moving a task

  1. Drag the bar to a new place. The task is pinned to these dates, and everything after it moves.
  2. To give a pinned task back to the planner, use the button Unpin in the task list.
  3. Reschedule calculates the whole schedule again.

The planner respects approved full days of leave: it does not put a task on a person on a day when they are away.

If you do not see …

  • Reschedule, or you cannot drag the bars — planning belongs to the roles Owner, Admin and Manager. Everybody else reads the schedule.