Project templates
A template says what one kind of job is made of: stages, tasks, their hours and their length. A new job is built from one of them. Open them in the menu Projects, in the settings at the bottom: Project templates.
Building a template
- Click New template (or open an existing one).
- Fill in Code, Name, Category and Usual lead time (days).
- Add stage — stages follow one another; each waits for the one before.
- Put tasks into a stage from the task catalogue with the button Place, or use Add task.
- For each task set Hours, and where needed Span (working days), Review, Lead review, On by default and the skill it needs.
- Click Save.
What you should know:
- Hours are how much work the task needs. Enter a length only when the bar lasts longer than the work itself.
- Inside a stage, tasks marked "at the same time" form a group that runs together; a task marked "after" starts a new group that waits for the group above it.
- A lead time, not work — a row with a length and no work, for example a delivery time.
- A task that is not On by default is put into a new job only when you tick it while you create the job.
- A template of the kind Plan has folders instead of stages, without dates.
Schedule preview
Above the tasks is the Schedule preview: how a job made from this template would be planned if it started on a Monday, in working days. It is drawn again when you change the template. The dates are only an example.
Retiring a template
A retired template is no longer offered for new jobs. Jobs already made from it stay.
If you do not see …
- New template and changes — templates are kept by the roles Owner, Admin and Manager. The role Office opens a template read-only, so it can choose one when it creates a job: the fields and buttons are switched off, Save is missing, and there is Back instead of Cancel. It sees the Schedule preview in the same way.
- Project templates in the menu — the roles Employee and Viewer do not read templates.
Next: Task templates · Related: New job